I will open the Status window for the Task4: complete, and I will get:Ĥ0% of 56 hours is 22,4 hours, and you can see this value in the Actual field, and the Remaining is 56-22,4 = 33,6 hours. In my previous blog I recorder progress for my three Tasks:Īs you can see, in this Table I have work in hours which is based on formula Duration in days X Hours per day. As I promised I will write about tracking actual work and cost on the Project in MS PROJECT 2010.